| T01Primary injection | CTs, protection and metering circuits, busbar / differential schemes | Proves CT ratio, polarity and the complete primary-to-relay circuit, and stability of differential schemes. | Primary injection report with ratio, polarity and stability results |
|---|
| T02Secondary injection | Numerical and electromechanical protection relays | Verifies pickup, operating characteristic and timing against the approved settings, through to trip outputs.Typical acceptance check · Operating times within the relay manufacturer’s stated accuracy for the applied setting | Relay test report and as-left settings file |
|---|
| T03Relay coordination | Feeder, transformer, bus and line protection | Grades protection so the device nearest the fault clears it first, with defined backup margins. | Coordination study, time-current curves and settings schedule |
|---|
| T04Oil filtration & BDV | Power transformers, reactors, oil-filled CTs | Dehydrates and degasses insulating oil by vacuum filtration; breakdown voltage confirms dielectric strength.Typical acceptance check · e.g. BDV ≥ 60 kV (2.5 mm gap) for EHV-class equipment before energisation, per applicable IS / IEC limits | Filtration log (temperature, vacuum, passes) and BDV results |
|---|
| T05Tan-delta & capacitance | Transformer windings and bushings, CTs, CVTs | Assesses insulation quality and moisture; establishes the baseline for condition trending.Typical acceptance check · Values compared with factory results; new insulation commonly below 0.5% | Tan-δ and capacitance report at test voltages |
|---|
| T06Insulation resistance & PI | Transformers, cables, switchgear, motors | Confirms insulation integrity; polarisation index indicates moisture and surface contamination. | IR / PI test sheets with test voltage and temperature |
|---|
| T07Winding resistance, ratio & vector group | Power and distribution transformers | Checks winding and tap-changer contacts, turns ratio on every tap and vector group.Typical acceptance check · Ratio deviation within ±0.5% of nameplate on each tap | Transformer test sheets per tap position |
|---|
| T08CB timing & contact resistance | Circuit breakers | Measures close / open times, pole discrepancy and main-contact resistance.Typical acceptance check · Within manufacturer’s published limits | Timing traces and micro-ohm readings |
|---|
| T09Earth resistance | Earth-mat grid and equipment earthing | Confirms the earthing system meets design resistance for safe step and touch potentials.Typical acceptance check · Commonly ≤ 1 Ω for large substations, per earthing design | Earth resistance test report (fall-of-potential method) |
|---|
| T10Statutory inspectorate approval | Complete installation | Inspection by the state Electrical Inspectorate against CEA safety regulations before the installation is charged. | Submission documents, inspection support and approval to energise |
|---|