Transformer tests before energisation
A power or distribution transformer is tested at site after erection to confirm that it has not been damaged in transport and that it matches its factory test results. Site results also become the baseline for condition monitoring over the transformer’s life.
- Insulation resistance and polarisation index (PI) of windings
- Winding resistance on every tap, which also checks tap-changer contacts
- Turns ratio on each tap and vector group verification; typical acceptance is within ±0.5% of nameplate
- Tan delta (dissipation factor) and capacitance of windings and bushings
- Magnetising current and magnetic balance checks
- Protection and alarm checks of Buchholz, oil and winding temperature indicators, PRV and OLTC